The Vishrantwadi Flyover Is Waiting on Two Temples, Not a Budget

GoVia Team · 23 Oct 2026 · 3 min read

The flyover that's waiting on two temples

On August 14, 2026, Pune Municipal Commissioner Naval Kishore Ram went out to inspect the flyover and grade separator going up at Mukundrao Ambedkar Chowk — the Vishrantwadi junction — and set a firm deadline: done by the end of December 2026.

What's actually standing in the way isn't funding, or land acquisition, or a contractor dispute. It's the Rameshwar Sheth Ganpati temple and the Mahalakshmi Devi temple, both sitting directly in the path the grade separator needs between Alandi Road and Airport Road. The commissioner ordered a joint inspection to sort it out within a month. Whether that happened on schedule isn't yet public.

A small project with a very Pune problem

This isn't a mega-project by the city's usual standards — ₹63 crore, first approved by Maha Metro back in August 2024, with soil testing starting in 2024 and construction only properly underway two years later. The flyover is meant to do something genuinely useful once it's finished: connect Airport Road and Alandi Road directly through Vishrantwadi, a junction that's been a chronic complaint point for residents for years (Ajit Pawar himself was out promising a fix for Vishrantwadi's traffic problems well before this project broke ground).

But the temple obstruction is the kind of thing that doesn't show up in a project budget line and doesn't resolve on an engineering timeline. Relocating or working around a functioning place of worship involves the community it serves, not just the contractor building the road — and that's exactly the sort of step that can quietly turn a "December 2026" deadline into something else entirely. The project also still needs its water pipelines and electricity cables relocated, which the commissioner separately ordered departments to coordinate.

Why this one's worth watching closely

Most delayed Pune infrastructure projects stall on money or paperwork — land acquisition disputes, tender delays, inter-agency coordination failures GoVia has covered before in Khadki, in Pashan, in a dozen corridors around the city. Vishrantwadi's holdup is different: it's a civic project running directly into the kind of local, human obstacle that no amount of budget or political will moves quickly, because moving it at all requires care, not speed.

What the commute looks like in the meantime

For anyone actually using Airport Road or Alandi Road through Vishrantwadi right now, none of this changes what today's commute looks like — a junction under active construction, with buried utility work and a still-unresolved temple relocation layered on top of whatever regular congestion was already there. A deadline that depends on a sensitive, unhurried negotiation is not a deadline you should plan your daily commute around. Until Vishrantwadi actually clears, sharing the ride through this particular stretch means one car absorbing the unpredictability instead of everyone separately discovering the day's detour at the barricade.