A Radio Telescope Just Killed the Direct Pune-Nashik Train Line
A radio telescope killed Pune's direct train line to Nashik.
That's not a metaphor for bureaucratic obstruction. It's the actual, literal reason. The Giant Metrewave Radio Telescope near Narayangaon — one of the world's largest, used by astronomers to listen for signals from deep space — sits close enough to the originally planned route that Indian Railways concluded the alignment was technically unviable. On June 17, 2026, Railway Minister Ashwini Vaishnaw confirmed the direct Pune-Nashik semi-high-speed line is scrapped. In its place: a revised route via Ahilyanagar and the temple town of Shirdi.
Five years of land acquisition, for a line that no longer exists
To understand how much this unravels, you have to know what was actually being built. This was a serious project: 234.60 km of double track, 24 stations, an estimated ₹16,039 crore budget, engineered to run at 200 kmph and cut the Pune-Nashik journey to two hours. Land acquisition for roughly 1,458 hectares across Pune, Ahmednagar, and Nashik districts started back in June 2021 — through direct purchase negotiations under state government resolutions, not forced acquisition.
The original alignment ran through a very specific, very real sequence of towns: Nashik, Sinnar, Sangamner, Akole, Narayangaon, Alephata, Manchar, Khed, Chakan, and into Pune. If you've ever driven the Pune-Nashik Highway through Chakan's MIDC belt, that's the exact corridor this line was meant to relieve.
Vaishnaw's announcement didn't erase the money or the work already done — he noted that substantial portions have already been sanctioned and construction has started on some sections. But a line "under construction in sections" with no confirmed through-route is a very different promise than "Pune to Nashik in two hours," and everyone along the original alignment knows it.
Nashik isn't taking it quietly
Local opposition groups — farmers, traders, industrialists, employees, and students along the original route — have called the Ahilyanagar-Shirdi detour exactly what it looks like to them: inconvenient and uneconomical. A Rasta Roko (road blockade protest) was planned in Nashik for August 9, 2026, specifically demanding the direct line be restored rather than rerouted around a telescope. Whether that protest changed anything isn't yet public, but the fact that it had to happen at all tells you how little goodwill survived the switch.
For Khed-Chakan-Manchar, the road was always going to matter — now it's permanent
GoVia has written before about Chakan's MIDC belt and the daily grind on the Pune-Nashik Highway and Chakan-Shikrapur Road that manufacturers there already deal with. What's changed is the ceiling on how much relief was ever coming by rail. A direct Pune-Nashik train was supposed to be the long-term pressure valve for exactly this corridor — pulling intercity traffic off the highway and onto rail. That valve just closed, rerouted toward Shirdi instead, for a timeline nobody's confirming.
That doesn't change what the highway is going to carry in the meantime: factory shift workers, suppliers, families making the same Pune-Nashik run Vaishnaw says is now a two-hour train journey only on a route most of them don't live anywhere near. If a project engineered specifically to take this exact load off NH-60 and the Chakan-Shikrapur stretch just got sent on a 40-kilometre-plus detour through Ahilyanagar, the road is what's actually carrying this corridor for the foreseeable future — and a shared ride splits that cost and fatigue in a way a solo commute never does.