Pune's Hinjewadi–Shivajinagar Metro Is Ready to Run. An Election Rule Is the Reason It Still Isn't.

GoVia Team · 4 Oct 2026 · 3 min read

Pune's Hinjewadi–Shivajinagar Metro Is Ready to Run. An Election Rule Is the Reason It Still Isn't.

The Commissioner of Metro Rail Safety cleared Pune Metro Line 3's first 12 stations for passenger operations back on July 23, 2026. PMRDA then scaled up its own opening plan, deciding to run trains to 17 of the corridor's 23 stations instead of just the original 12. By every engineering measure that matters, the 23.3km line connecting Rajiv Gandhi Infotech Park in Hinjewadi to Shivajinagar is built, tested, and signed off as safe to carry passengers.

It still isn't carrying any. The launch has been pushed back again — this time because the Model Code of Conduct for the Maharashtra Legislative Council elections is now in force, and stays in force until the end of October 2026. Under MCC rules, a big public infrastructure launch tied to a sitting government reads too much like campaigning, so the inauguration waits. Even once that window closes, there's a second dependency stacked on top of it: Chief Minister Devendra Fadnavis has said Prime Minister Narendra Modi was invited to inaugurate the line virtually, which means the actual date now also depends on finding a slot in the Prime Minister's own schedule.

A line with a long memory of slipping dates

This isn't the project's first delay. An early target had the Hinjewadi-Shivajinagar stretch opening by March 2026. That slipped to May, then to June 15. CMRS clearance for the first 12 stations didn't land until July 23 — well past all of those. Through August and early September, reporting consistently used the same hedged language: "likely," "expected," "PMRDA expects." Nobody, at any point, was describing a line that had actually started running. Now it's the election calendar doing the delaying, with a confirmed date still nowhere in sight.

None of this is a knock on the engineering. A fully-built metro line sitting idle because of an election rule and a scheduling dependency is a bureaucratic problem, not a construction one. But if your commute runs along this corridor — Wakad, Balewadi, Baner, into Shivajinagar — "the metro is basically ready" has been true for months now, and it still hasn't moved a single one of your actual commutes.

That's the gap carpooling has been filling the entire time this metro line has been stuck in "almost." It doesn't wait on CMRS clearances, election codes, or a Prime Minister's calendar. Someone driving from Baner to Hinjewadi's IT park today, with an empty seat, solves the exact same trip the metro is eventually supposed to solve — just without a launch date attached to it. When Line 3 does finally open, it'll genuinely help. Until then, the people who needed this corridor solved in 2026, not whenever the inauguration gets scheduled, already have a way to do it.