Three Missed Deadlines Later, the Dairy Farm Bridge Is Finally Open

GoVia Team · 12 Nov 2026 · 3 min read

Deputy Chief Minister Sunetra Pawar cut the ribbon on the Dairy Farm railway overbridge in Pimpri this week - a four-lane crossing that has been "almost ready" for so long that PCMC had to issue its own contractor a warning letter over it just three months ago.

The timeline is worth laying out plainly, because it explains why this opening matters more than a routine ribbon-cutting. The work order for this bridge was issued in March 2023. By March 2025 - two years in - the project was 55% complete, slowed in part by trees that had to be cleared from the construction path. It then missed a second deadline, and in August 2026, PCMC formally warned the contractor of a financial penalty after a third deadline slipped. Three years and eight months after that original work order, the bridge finally opened to traffic this week.

What it actually does is simple and specific: it lets vehicles cross the Pune-Lonavala railway line near the Military Dairy Farm without stopping for a train. That crossing - Level Crossing No. 60 - is being permanently closed now that the bridge is open, according to officials quoted in local coverage. The bridge connects Pimpri to Pimple Saudagar, Rahatani, and Kalewadi, areas that have grown dense enough that a railway gate closing for even a few minutes at the wrong time could back up traffic for considerably longer. It cost roughly Rs 65.28 crore. (Reports disagree on its exact length - one account puts it at 565 metres, another at 1,290 metres - so take the precise figure with some caution; everyone agrees it's four lanes with a separate footpath.)

For anyone who has ever tried to time a shared ride through this stretch of Pimpri, the old crossing was the kind of variable you couldn't plan around. A train could be two minutes out or twenty; there was no way to know until the gate came down. If you were coordinating a carpool - say, splitting the Pimpri-to-Hinjewadi commute with a colleague, or arranging a shared drop near Kalewadi before a flight - you built in slack time for that crossing specifically, the way you'd build in slack for a flaky traffic signal. That's gone now, for this crossing at least. It won't fix Pune's broader congestion problem, but it removes one specific, well-known unknown from one specific commute - which is exactly the kind of small, measurable win that rarely gets a headline on its own, but adds up for the people who actually drive through there every day.

If you're one of them and you're tired of driving that stretch alone - or you've got something small to send across town rather than drive it yourself - that's precisely the kind of short, predictable hop GoVia's carpooling and parcel-sharing features are built around.

Ready to try GoVia?

Share rides, join bike pools, and send parcels with trusted travelers near you.

Download the GoVia app