Pune's Balewadi-Wakad Bridge Was Finished in 2019. It's Still Closed Over 200 Square Metres of Land.
Pune Municipal Corporation finished building the bridge connecting Balewadi to Wakad across the Mula River back in 2018-19. Depending on which report you read, it cost somewhere between Rs 25 crore and Rs 31 crore, and was complete by either 2019 or August 2021 - the numbers disagree with each other almost as much as the bridge disagrees with being used. What nobody disputes: it has sat closed for most of the time since, blocked by roughly 200 square metres of private land that PMC never actually acquired before pouring the concrete around it.
One landowner holding out for compensation got a court stay on the acquisition, and that stay held for years. It took until February 2026 for the Bombay High Court to lift it and order PMC and the state government to move, with a one-year deadline to acquire around 10 guntha of land near Kaspate Vasti in Baner. In April, the district administration followed through with an actual acquisition notification, this time for a 30-metre-wide Development Plan road meant to carry traffic onto the bridge from the Baner side. Seven years after the concrete was poured, the paperwork is finally catching up to it.
That's where the story takes its real turn. By May, as word spread that the bridge might genuinely open this time, the Baner-Balewadi Nagrik Manch didn't celebrate - they wrote to the Municipal Commissioner asking for a full traffic impact study, done jointly with Pune Traffic Police, before anyone opens it to vehicles. Their argument: internal roads like Mamta Chowk, Balewadi High Street and Dasara Chowk are already absorbing traffic from a construction boom of high-rises and commercial towers that went up faster than any parking or widening plan did. A new river crossing dumping more cars onto those same junctions, they said, could make things worse before it makes them better. (If Baner-Balewadi sounds familiar from elsewhere on this blog - new signal timings on the High Street, an e-bus charging pilot nearby - this is a different animal entirely: not signal timing or charging infrastructure, but whether a finished piece of concrete should even be allowed to open yet.)
By July, reporting described the bridge as still closed - not finished-and-waiting, but genuinely closed, with construction debris and garbage piling up across a deck that's been structurally done for the better part of a decade. August coverage still described the same peak-hour gridlock on the approach roads, and still no sign of that traffic study. Whatever becomes of the one-year court deadline from February, nothing found since suggests the land has actually changed hands, the study has actually happened, or the bridge has actually opened.
There's a bigger elevated-road plan for the same general corridor too - a six-lane project through Wakad, Balewadi and Baner meant to eventually take pressure off the Mumbai-Bengaluru highway traffic running through here - but that one is still a proposal, nowhere near even the closed-bridge stage.
What almost nobody in this story is asking is the one question that would matter regardless of how the land dispute or the traffic study turn out: how many of the cars that eventually cross that bridge actually need to be separate cars. A shared ride across the Mula River is one fewer vehicle at exactly the junctions everyone's worried about - the only fix here that doesn't depend on a court deadline, a land survey, or someone finally hauling away seven years of debris.